Not sure what your scheme will owe?
Send us your project and where it is. A Senior Architect will give you an initial appraisal and guide you as to what to do next.
Start a conversationCharged per square metre, triggered when work starts.
The Community Infrastructure Levy is a charge per square metre of new floorspace, set by councils that adopt it. New homes and most schemes adding 100 square metres or more pay it. Self-build homes, annexes and larger extensions can be exempt, if the exemption is granted before work begins.
The levy is charged on new floorspace, net of what was already there and in use. On this scheme the first liability notice missed what was already there.
A shop at Shirley, in Solihull, converted and extended to eighteen apartments, with commercial space on the ground floor. Most of the finished floorspace was the existing building, kept and converted. It had been in lawful use in the three years before permission.
The first liability notice counted the whole development as new floorspace. We sent a corrected additional information form showing the existing building kept, converted and in lawful use. The council issued a revised notice the next day.
The rest followed the sequence. Liability was assumed when the council asked for it. The commencement notice went in before the notified start in June 2021, the demand notice followed, and the levy was paid on time with no surcharge.
The lesson is about evidence as much as forms. The deduction for an existing building depends on showing it was in lawful use for a continuous six months in the three years before permission. Without that evidence, a council can treat the building as not in use.
A liability notice can be reviewed and appealed, but only within fixed periods and only before work starts. Getting the form right first is quicker than either.
A self-build house in Sandwell. We prepared the assumption of liability, the exemption claim and the commencement notice; the council granted the exemption and replaced its first liability notice with a nil one before the notified start.
Five homes in a redundant fertiliser barn, first approved under Class Q in 2023. That prior approval was liable to the levy like any permission, but the barn had been in use, so its floorspace was deducted, the charge came out nil and no commencement notice was needed. A full permission followed in June 2026, with the prior approval as its fallback.
Four new homes replacing a house and its outbuildings in a Warwickshire village. They had been in lawful use, so existing floorspace was deducted and the notice on the varied permission came back nil, with no commencement notice needed.
A house in multiple occupation in Leamington, consented in 2025 as eight flats inside the existing building. Our additional information form showed the whole building kept and in use, with no new floorspace. The council wrote that no levy was due.
Every planning application we make in our own name is a matter of public record on a council register, and ours reach more than 100 planning authorities across the UK.
Architects for developers →Send us your project and where it is. A Senior Architect will give you an initial appraisal and guide you as to what to do next.
→ Start a conversationNot every council charges the levy. Adopting it is a choice and a council that has done so publishes a charging schedule, with rates that can vary by area, use and size of development. Where no charging schedule applies, there is no levy to pay; in London the Mayor's levy applies on top of any borough's.
Where there is one, look at what the scheme adds. Less than 100 square metres of new floorspace pays nothing, unless it creates a new home; splitting one house into flats, with no new floorspace, is not charged.
In June 2026 the government put the number of authorities charging it at 164, which it called over half of England's planning authorities. A schedule can set a zero rate for some uses or zones, so a council that charges the levy may still charge nothing for the scheme in hand; its annual rate summary gives each year's figures.
Conversions can pay little or nothing. The charge is on the whole scheme less any kept floorspace that qualifies. Kept floorspace qualifies where the building has been in lawful use for long enough, a rule that can decide whether a conversion pays anything at all.
Four rules do most of the work, all set in regulations; each can turn a large bill into a small one or the reverse.
Each charging authority sets rates per square metre of gross internal area, which can vary by use and zone and are indexed to building costs. The charge is the indexed rate times the floorspace, less any that qualifies for deduction.
Floorspace in an existing building can be deducted where part of it was in lawful use for a continuous six months in the three years before permission. Demolished floorspace counts only from buildings that were in use.
Self-build homes, residential annexes and larger extensions to your own home can be exempt; there are reliefs for social housing and charities. Each has its own conditions and a claim form, though the two reliefs share one.
The levy is triggered once development commences and the council has to be told the start date beforehand with a commencement notice. Without an instalment policy, the whole sum is due within 60 days of the notified start.
Rates are re-indexed every January and each council publishes its own. On the same new house the levy can run from nothing to more than £46,000, depending on the council and the zone.
The figures assume a new house on a plot with no building in use, permission granted in 2026 and no exemption; the council's liability notice gives the exact sum. A self-build home that claims the exemption before work starts pays nothing.
The residential rates for permissions granted in 2026, per square metre of new floorspace, from each council's own statement:
Zones follow each council's charging map, so check the site on the map rather than by town name. Several councils charge more per square metre on small schemes in the villages than on large ones, so a single house can pay more than a home on a big estate nearby.
Schedules are reviewed from time to time. A new joint schedule for Worcester, Wychavon and Malvern Hills was at examination in October 2026, so check the council's own page before relying on a figure here.
The rate charged uses the index for the year permission is granted, so a scheme permitted in an earlier year pays that year's rate. The figures here are for 2026; each council must publish the next year's rates in December.
Money can be lost on the levy through paperwork alone, as the government acknowledged in June 2026. It runs on a fixed sequence of forms and the order matters as much as the content.
With the planning application goes the additional information form, setting out the existing floorspace, its use and the new floorspace. Then someone assumes liability, so the council knows who is paying; if nobody does, it can look to the owners of the land.
Where an exemption applies, its claim goes in and is decided before work starts; a self-build claim also needs liability assumed first. Then the commencement notice goes in, no later than the day before work begins. On permitted development, with no planning application to start the process, a notice of chargeable development has to reach the council first.
After that the council issues a demand notice. For a self-build home there is one more step: the evidence of completion and occupation, within six months of the completion certificate.
Whoever assumes liability, such as the developer or the landowner. If nobody does, liability falls on the owners of the land.
Anyone may assume liability for the levy, on an assumption of liability form: ideally with the planning application and in any case before work starts, because it cannot be assumed afterwards. The council then issues a liability notice setting out the amount. If nobody has assumed liability when work starts, the levy is split between the owners of the land, surcharges can be added and the whole sum is due at once. That matters most where the person building is not the person who owns the land, because the default puts the bill on the owner.
Not if it adds under 100 square metres. A larger extension to your own home can be exempt if claimed and decided before work starts.
The threshold is the gross internal area of new build; an extension below it pays nothing without any claim. At 100 square metres or more, the residential extension exemption from CIL covers an owner who lives in the house, claimed on its own form. If work starts before the council decides the claim, the claim lapses and the levy is due. Unlike the self-build and annex exemptions there is no clawback and no commencement notice is needed. Garden rooms and outbuildings count as floorspace if they are buildings people normally go into.
CIL can be payable: the levy applies to permitted development too. A barn conversion needs a notice before work starts unless nothing is due.
The levy applies to development permitted by the national order as well as by planning permission. The notice of chargeable development goes to the council. Whether anything is due depends on the new floorspace and on the building's use. The deduction for existing floorspace applies only where the building was in lawful use for a continuous six months in the three years before the development is permitted; a redundant farm building may not have been. In June 2026 the Valuation Office allowed no deduction at all for a barn regularised by a retrospective permission. The notice is easy to miss on permitted development, because a prior approval is not a planning application and may not prompt it. Schemes adding under 100 square metres and no new home need no such notice; nor do exempt home extensions.
Within three years of the completion certificate, a sale withdraws the exemption and the levy becomes payable as if never granted.
The period runs for three years from the completion certificate. The exemption rests on the person who built or commissioned the home living in it as their sole or main residence. Selling it, letting the whole of it or it ceasing to be self-build housing within the three years ends the exemption; the person who had the exemption must tell the council within 14 days. In 2025 the High Court held that a sale before the home is finished counts too. The CIL exemption also needs a second form, with the evidence of completion and occupation, within six months of the completion certificate.
No. Affordable housing is not infrastructure for levy purposes, so it is secured through a section 106 instead.
Where a council charges the levy, it helps fund general infrastructure such as roads, schools and open space; a section 106 covers affordable housing and needs specific to the site. Since 2019 both can fund the same item. CIL is a fixed charge per square metre set in advance, while a section 106 is negotiated for each scheme and an obligation can only count towards the permission where the scheme needs it. A scheme can pay both; the negotiation that matters on a section 106 is covered in the guide to section 106 agreements.
Yes, but the amount can only be challenged before work starts: a council review within 28 days, then a Valuation Office appeal within 60 days.
Both periods run from the date of the liability notice. Neither a review nor an appeal on the amount is possible once development has begun; an appeal lapses if work starts before it is decided. Surcharges are appealed separately, to the Planning Inspectorate. In 2026 the High Court refused to let a developer reopen floorspace it had not proved within those periods. The arguments that move a CIL amount are about floorspace, what counts as existing and whether a building was in lawful use for long enough, so the evidence belongs with the application.
An annex can be exempt if it forms one new dwelling wholly within the main house's curtilage, claimed and decided before work starts.
The CIL exemption is for an owner who lives in the main house. It is claimed on its own form and needs a commencement notice before work starts. It can be clawed back for three years from the completion certificate if the annex is let, either is sold on its own or the house stops being a single dwelling. Accommodation that is not a separate dwelling and adds less than 100 square metres pays nothing in any case.
Not by October 2026. The Infrastructure Levy in the Levelling-up and Regeneration Act 2023 had not been brought into force.
In November 2025 the government said it did not intend to commence it. Councils that charged CIL therefore went on doing so under the 2010 regulations; the rules on this page were those in force when it was checked. In June 2026 the government said it would consult on changes so that householders and self-builders are not charged because of procedural errors; no consultation had been published by mid-October 2026.
Each rule here comes from the sources below.
Rickett Architects
A RIBA Chartered practice, working since 1970, with more than 2,500 projects behind it. Our senior architects take projects from first survey through planning to completion, for private clients, developers and landowners across the Midlands and well beyond it.
Tell us about your project
A Senior Architect will reply. We will give you an initial appraisal and guide you as to what to do next.