Class MA Permitted Development: Commercial to Residential

With two continuous years of Class E use, an office or a shop in England can become homes without a full planning application.

Reviewed November 2026
The short answer

Class MA turns a commercial building into homes through prior approval. The council can check up to nine matters and has 56 days to decide. Each home must meet the nationally described space standard.

Have a building in mind? Send us the address →
In practice · Sheldon Court

Two office blocks, taken to apartments.

Photograph of the completed Sheldon Court, Birmingham: red brick, grey window frames and two orange entrance features
Sheldon Court: a photograph of the completed building.

Two empty office blocks in Birmingham, bought with a Class O prior approval already in place. The design and the building work were still to do.

How the job ran
01Prior approvalClass O, for 64 apartments. Granted on 25 November 2019.
02AppointedJanuary 2020, for the design and the design warranty.
03Five applicationsAmong them external alterations, approved in April 2020.
04Built and letBy a contractor. Last drawings March 2021.

Class O was the office-to-homes right before Class MA. The prior approval came with the buildings and Rickett Architects was appointed afterwards.

The job
Site
Wagon Lane, Sheldon
Homes
58 one-bedroom, 6 two-bedroom
Role
Full architectural design and the design warranty
Outcome
Built and let
View project →

The building work then took five further applications, among them one for external alterations and one to discharge a materials condition. A Class MA scheme is the same: the outside works usually need permission of their own.

More

The design meant working drawings for both blocks, 3,221 square metres in all. A contractor built the scheme. The last drawings were issued in March 2021.

Visualisation of Sheldon Court in its office years, from the same viewpoint, with green window frames and a tall glazed entrance porch
Before the conversion: a visualisation reconstructed from a historical reference image, from the same viewpoint as the photograph above.
The proof

Commercial buildings, taken to homes.

Visualisation of 62 Brandon Parade, Leamington Spa: the pale Willes Road facade under a grey mansard
Visualisation; the finish is illustrative.
Class O prior approval, then works permissions

Brandon Parade

An office building in a conservation area, taken to 15 apartments. The change of use was a Class O prior approval in 2019. The works then needed their own permissions.

Leamington Spa
View project
Visualisation of 342 Stratford Road, Shirley: three white gables over a glazed commercial frontage
Visualisation of the finished scheme.
Full planning permission, shop to 18 homes

342 Stratford Road

A three-storey furniture store on the A34, converted and extended into 18 apartments with a commercial unit kept at the street front. Rickett Architects was architect and planning agent. Full planning permission was granted on 5 February 2021. That was before Class MA applications opened on 1 August 2021.

Shirley, Solihull
View project
Enhanced photograph of the 1906 red-brick cycle works on Foleshill Road, Coventry, under a dark metal top storey
Enhanced photograph of the works.
Planning permissions, conversion and new block

Foleshill Road

A locally listed 1906 cycle works has planning permission for 24 apartments. A new block beside it has ten studios. Rickett Architects was appointed delivery architect for the conversion in early 2022. The scheme was around 70 per cent built by mid-2026.

Coventry
View project

Every planning application we make in our own name is a matter of public record on a council register and ours reach more than 100 planning authorities across the UK.

Architects for office to residential conversions →
The first step

Not sure if your building qualifies?

Send us your project and where it is. A Senior Architect will reply with a view on what to do next.

Start a conversation
01 · Where you stand

First, check whether this is your route.

Class MA is a permitted development right, not a use class. It lets a building in a Class E use, such as an office, a shop or a clinic, become homes without a full planning application. You still apply to the council first. The difference is the scope: the council can look only at the matters the right lists.

The first job is to test the building against the limits below. Most of that can be checked from a desk, with the address and the council's maps. The use history is different. It needs records from the owner, such as leases or business rates bills, that show two years of Class E use.

More

For a commercial to residential conversion Class MA took over from the old office-to-homes right (Class O) and from the old right for some shops and financial services buildings (Class M). The last Class O applications had to be made by 31 July 2021 and Class MA applications opened the next day, on 1 August 2021. The homes it makes fall in Class C3.

The right covers the building and any land within its curtilage. It does not matter whether the building was an office, a shop or a clinic, as long as the use falls in Class E and the building passes the limits below. Class MA can make flats as well as houses. The council decides whether its prior approval is needed and, if it is, whether to give it.

02 · The limits

Where Class MA stops.

The building has to pass on its use, where it stands and the size of its homes. An Article 4 direction can take the right away altogether.

Limit 01

How it was used

The building must have had a Class E use, such as a shop, an office, a cafe, a gym or a clinic, for at least two years in a row before you apply.

What it means: the building can still be in use when you apply. The vacancy test was removed on 5 March 2024.
Limit 02

Where it stands

It does not work for a listed building, a building in its grounds or a scheduled monument. Nor does it reach a site in a National Park, the Broads, a World Heritage Site or an area of outstanding natural beauty.

What it means: a conservation area does not rule it out. The council looks at the area only for a ground floor change.
Limit 03

How big and how small

There is no upper limit on the size of the building or the number of homes. Each new home must be at least 37 square metres and meet the nationally described space standard. A very large scheme may need screening under the environmental impact assessment rules.

What it means: a large office block can qualify. Each home is measured on its own.
Limit 04

The council's checks

The council can look at up to nine matters, among them transport, contamination, flooding, noise from commercial premises and natural light. Fire safety joins them where the building will hold two or more homes and is at least 18 metres high or 7 storeys.

What it means: the council must refuse if any habitable room lacks adequate natural light.
More

The right also does not reach a site of special scientific interest, a safety hazard area, a military explosives storage area or an area the Secretary of State has specified under section 41(3) of the Wildlife and Countryside Act 1981. The Order says area of outstanding natural beauty. The National Planning Policy Framework published on 17 August 2026 calls these areas National Landscapes and defines them as areas legally designated as areas of outstanding natural beauty. If the site is occupied under an agricultural tenancy the landlord and the tenant must both give express consent.

The nine matters are transport impacts and safe site access; contamination risk; flood risk; noise from commercial premises on the people who will live there; the effect on a conservation area of losing ground floor use; adequate natural light in all habitable rooms; the effect on future residents of homes in an area the council sees as important for general or heavy industry or waste management or storage and distribution; the effect on local provision of losing a registered nursery or an NHS health centre; and fire safety. Three of the nine arise only where the Order says so. Those are the ground floor in a conservation area, the loss of a nursery or health centre and fire safety. A fourth, the industry area matter, arises only where the council sees the area as important for industry, waste or storage.

Fire safety is a prior approval matter only where the building will hold two or more homes. It must also be 18 metres or more in height or have 7 or more storeys. In that case the application must include a fire safety statement and the council must consult the Building Safety Regulator. Before 27 January 2026 the Health and Safety Executive held that role. Height is measured from ground level to the top floor surface of the top storey. Storeys below ground level do not count.

There is no size limit, with one caution. A very large scheme can fall under the environmental impact assessment rules. It can then use the right only if the council or the Secretary of State has decided that no assessment is needed.

03 · The scope

Change of use, not building works.

Class MA lets the building become homes. It does not give permission to change the building itself. New windows, new doors and an extension usually alter the outside enough to need their own permission, unless another permitted development right covers them. Allow time for those applications.

Building regulations still apply to the conversion. Once the homes exist, the usual householder rights to extend or alter them do not apply where Class MA is their only permission.

More

The application must still show what is proposed. The floor plans must give the floor area of each home in square metres. They must show the size and use of each room and the windows and doors and walls. The elevations of the homes must be shown too.

The council can ask for details of building or other operations when it decides the prior approval. That does not give permission for them.

04 · The process

The application and the 56 days.

Class MA prior approval is one application and four steps.

The order of work
01ApplyDescription, plans, floor plans and the council fee.
02NoticeSite notice or neighbour letters. Consultees get at least 21 days.
03DecisionThe council has 56 days, or longer if agreed in writing.
04BuildFinish within three years of the prior approval date.

The council can approve with or without conditions, as long as each one relates to the matters it checked. After the conversion the building has to stay in use as homes.

More

The application needs a written description of the development, a plan of the site and a statement of the net increase in homes. It needs floor plans. It needs the applicant's contact address and an email address if the applicant is content to be contacted that way. It needs a site-specific flood risk assessment where the Environment Agency must be consulted. For a tall building that triggers fire safety it needs a fire safety statement. The council fee goes with it. The council can refuse an application that does not give it enough information to check the scheme against the right.

The council must publicise the application. It can put up a site notice for at least 21 days or serve notice on the adjoining owners and occupiers. Public holidays do not count towards the 21 days of a site notice. Consultees get at least 21 days to reply. The Environment Agency is consulted for flood zones 2 and 3 and for certain flood zone 1 areas. The highway authority is consulted where the council thinks the scheme will materially increase traffic or change its character on a trunk road or a classified road. A council that is itself the local highway authority does not consult. The rail operator is consulted for a level crossing.

The work must be finished within 3 years of the prior approval date. That is the date prior approval is given or the date the council says none is needed. If the council makes no decision it is the date the decision period ends. After the conversion a use ancillary to the homes is allowed as well.

Common questions

Class MA, answered.

How long does Class MA prior approval take?

The council has 56 days from the day it receives the application.

More

The period can be longer if the applicant and the council agree it in writing. If it ends with no decision the work may start. The work must then follow the details in the application. Silence does not help a scheme that falls outside the limits of the right. Work may start sooner if the council gives prior approval or says none is required.

Can an office be converted to flats without a full planning application?

Yes, through Class MA. You must first apply to the council.

More

Class MA can make flats as well as houses. The building must have been in Class E use for at least two continuous years before the application. It must not sit in a place the right excludes. The council then has 56 days to decide.

Can a listed building or a building in a conservation area use Class MA?

A listed building cannot use Class MA. A conservation area does not rule it out.

More

Neither can a building in the curtilage of a listed building. If the building is in a conservation area and the change involves the whole or part of the ground floor the council can look at the effect on the character or sustainability of the area. A listed building needs a planning application instead. Works that affect its character need listed building consent too.

Is there a size limit on a Class MA conversion?

No. Class MA sets no upper limit on size or on the number of homes.

More

Two tests were removed on 5 March 2024. One was the 3-month vacancy test. The other was the 1,500 square metre floor space limit. Each new home must still be at least 37 square metres and meet the nationally described space standard. A very large scheme can fall under the environmental impact assessment rules. It can then use the right only if the council or the Secretary of State has decided that no assessment is needed.

What is the minimum home size under Class MA?

A new home cannot have a gross internal floor area below 37 square metres.

More

It must also meet the nationally described space standard. That standard sets a minimum floor area by the number of bedrooms and people a home is designed for. Check it for each type of home before the layouts are drawn.

Can the council take Class MA away?

Yes, in an area it chooses, by making an Article 4 direction.

More

A council that wants to remove the right makes a direction. It must give public notice and take account of local views before the direction is confirmed. The council can also make a direction take effect straight away. That direction ends after six months unless the council confirms it. A direction does not affect work if the prior approval date falls before the direction comes into force. The work must be finished within 3 years of the prior approval date. The National Planning Policy Framework published on 17 August 2026 says a direction should be based on evidence and cover the smallest area needed. A council does not have to pay compensation if it publishes notice of the direction at least 12 months and no more than 2 years before the direction takes effect. That applies only to work that had not started when the notice was published.

When is a full planning application better than Class MA?

When the scheme needs more than a change of use.

More

A full application suits building works beyond the change of use. It also suits a building in a place the right excludes and a scheme the right will not allow. The council then decides it under the development plan and other material considerations. It does not apply a fixed list of checks.

How much does a Class MA prior approval application cost?

The council charges a fixed fee for each home the application proposes.

More

For applications made from 1 April 2026 to 7 December 2026 the fee is £260 for each home. For applications made on or after 8 December 2026 it is £323 for each home until the next uprating. The fee is uprated each 1 April if consumer prices have risen. The next date is 1 April 2027. Ten flats would cost £2,600 under the first fee and £3,230 under the second. The council or the Planning Portal will have the current figure. These are council fees only. The cost of the works, VAT and finance sit outside this guide.

Sources

Where this page comes from

Every rule here was read in the Order on 20 November 2026, as updated to 21 October 2026. The last change to Class MA it showed was dated 27 January 2026.

Checked 20 November 2026
Order
General Permitted Development Order 2015, Schedule 2, Part 3, Class MA
Procedure
Paragraph W and article 7, prior approval and the 56 days
Article 4
Article 4 of the Order and Schedule 3, directions
Fee
S.I. 2026 No. 1192, in force 8 December 2026
Our record
Our own job files for the four schemes on this page
Written by

Rickett Architects

A RIBA Chartered practice, working since 1970, with more than 2,500 projects behind it. Our senior architects take projects from first survey through planning to completion, for private clients, developers and landowners across the Midlands and well beyond it.

Nationally described space standards → Changing what a building is used for → What permitted development allows →

Tell us about your project

Thinking about a commercial building?

A Senior Architect will reply. We will give you an initial appraisal and guide you as to what to do next.