Brownfield land, made buildable.

Where a consent and a buildable scheme part company.

Reviewed August 2026
The short answer

Brownfield land carries real policy weight in England, and that is the easy part. What decides a scheme is the ground, what crosses the site and the cost of clearing what stands. None of that is settled by the permission.

In practice · Coventry

A consent that could not be built

The clearest way to explain a brownfield site is to watch one permission meet the ground.

The order of work
01Survey the groundThe plot investigated before detailed design began.
02Find what crosses itA live cable, with a metre of clearance each side.
03Design to the constraintThe building stepped back off the clearance line.
04Consent again, then buildA fresh full permission, and now in construction.

A corner plot on a long brownfield frontage at Foleshill Road in Coventry, inside the Coventry Canal Conservation Area and next door to a locally listed works of 1906. Our client, a Midlands buy-to-rent developer, had bought it with a permission already on it for twenty-three studio apartments.

The job
Site
A corner plot on a brownfield frontage, in a Coventry conservation area
Role
Architect, and the named applicant
Consent
Coventry City Council ref FUL/2022/2402, granted January 2024
Outcome
Ten studios in a four-storey building, in construction

That permission was not buildable. When the ground was surveyed at the start of detailed design, a high-voltage power cable came to light that no drawing had accounted for, running north and south with a metre of clearance required on either side of it. The consented footprint sat across it.

More

So the plot was designed again from nothing, around the easement rather than over it. The new building steps back off the clearance line: four storeys and 11.75 metres on a site of 267 square metres, ten studios of twenty-three to forty-one square metres. A fresh full application went in, and Coventry City Council granted it in January 2024.

Ten that could be built, against twenty-three that could not. The building is now in construction.

What took the time was not the drawing. A section 106 agreement securing the tenure of the studios ran for roughly a year before the council could issue a decision, and a period like that appears in no statutory timetable.

The easement did the design some good in the end. Stepping the corner back cut the apparent bulk of the new building and left the listed works the dominant thing on the street, which is the argument the heritage statement then had to make. A constraint found at the right moment is a design brief. Found six months later it is a write-off.

The proof

Five brownfield sites, five roles.

Former gas works · consented

Newbold Road, Rugby

A former gas-holder site in Rugby, consented for ninety-eight homes and then for a hundred and twenty-two. Architect on both consents. Decontamination came in higher than anyone had priced, so the building was drawn again and taller, on a fresh full application rather than a variation. Contaminated ground is a cost, not a bar.

Rugby Borough Council refs R17/2113 and R19/1496 · 98 homes consented 2018, 122 granted at committee August 2020
Commercial to housing · granted

Cross Street, Leamington Spa

A worn-out commercial building on previously developed land in a conservation area. It already carried a prior approval to convert the offices to flats. That fallback was set aside, the building taken down, and a full permission won for eight apartments instead: architect and agent at every stage, feasibility to sales.

Warwick District Council ref W/22/1546 · granted at committee January 2023
Reserved matters · delivered

Merton Street, Banbury

A town-centre site in Banbury previously in industrial and market use, redeveloped as a hundred and thirty apartments and six commercial units across six blocks. The outline permission was already in place. The reserved matters scheme was drawn, and permitted at committee, and all six blocks were then drawn for construction.

Cherwell District Council ref 04/02630/REM · granted June 2005
Remediation · discharged

Muller Yard, Nottingham

A former dairy depot of about half a hectare beside the Trent, in Flood Zone 3, redeveloped as fifty-eight homes with ground-floor retail. The permission arrived with remediation conditions attached to the ground and the groundwater. Those were discharged, and the buildings taken from technical design through to handover.

Nottingham City Council ref 23/01477/PDS4 · remediation verified and discharged, 2023
Part demolition · granted

34 Windsor Street, Burbage

A town-centre plot where part came down and part stayed up: two dwellings made out of what already stood, four new ones built behind it. The public house on the same site became a dwelling in its own right fourteen months later. Demolition is a decision taken building by building.

Hinckley and Bosworth Borough Council refs 19/01105/FUL and 20/01298/FUL · granted November 2019 and February 2021

Every planning application we make in our own name is a matter of public record on a council register, and ours reach more than 100 planning authorities across the UK.

Architects for developers →
The first step

Not sure a brownfield site will build?

Send us your project and where it is. A Senior Architect will give you an initial appraisal and guide you as to what to do next.

Start a conversation
01 · Where you stand

First, check whether the land is brownfield

Brownfield is not a description of how a place looks. It is a definition, and the national glossary sets it out precisely: land that has been lawfully developed and is or was occupied by a permanent structure, together with the fixed surface infrastructure that goes with it and the curtilage around it.

More

That definition was widened in December 2024 to take in large areas of hardstanding which have been lawfully developed, which brings a good deal of yard and car park in with the buildings. What it still excludes is where most of the argument happens: land last occupied by agricultural or forestry buildings, minerals and landfill sites where restoration was provided for through development management, residential gardens, parks, recreation grounds and allotments, and land where the remains of what once stood have blended back into the landscape.

It matters because the policy support attaches to the definition rather than to the impression. A farmstead is largely outside it however much concrete is on the ground, and so is a garden however large. A redundant depot on the edge of a village is squarely inside it.

Two separate things ride on the answer, which is why it is worth settling first. One is the policy weight the site attracts. The other is eligibility for a brownfield land register, and the permission in principle a register entry can carry with it. Both are read against the same glossary entry, and both are lost if the land turns out to fall in one of the exclusions.

There is a second reading worth doing on the same afternoon. A site can satisfy the definition and still be the wrong site: land in a flood zone, land where a valuable habitat has established itself over years of neglect, land where remediation costs more than the homes will be worth. Being brownfield is a policy advantage. It is not a survey.

02 · The abnormals

Where the money actually goes

Four costs decide most brownfield schemes, and the planning permission settles none of them. All four are priced after consent, which is exactly when a scheme has least room to move.

Cost 01

What is in the ground

Contamination reaches the planning system only so far as another regime does not already deal with it, and the standard is suitability for the proposed use rather than a pristine site. After remediation the land must at least not be capable of being determined as contaminated land under Part IIA.

Where it fails: a desk study prices nothing. The remediation figure arrives with the intrusive work, by which time the scheme is fixed.
Cost 02

What crosses the site

An easement is a right recorded in the title, not a line on a consented layout, and the permission does nothing to move it. Diverting the apparatus runs to the utility's timetable rather than yours, and until it moves the clearance corridor takes developable area out of the middle of the plot.

Where it fails: a permission can be granted over an easement. A building cannot be built over one.
Cost 03

What has to come down

Demolition is the visible half of the bill. The invisible half is what sits under it: slabs, old foundations, tanks, basements, buried obstructions and asbestos in fabric nobody has opened. On ground that has been built on twice, the earlier set of foundations is usually still down there.

Where it fails: the cost of taking a building down is not the cost of taking out what is beneath it.
Cost 04

What the levels do

Made ground raises a site above whatever everything around it drains to. Once the levels are surveyed properly, retaining structures, drainage falls, thresholds and access gradients all move together, and each of them moves the others. Very little of this is visible on a flat-looking plan.

Where it fails: two metres of imported fill turns a flat plan into retaining walls, and no consent pays for those.
Common questions

Brownfield, answered

Does brownfield land get preferential treatment in planning?

Yes, and unusually explicitly. National policy gives substantial weight to using suitable brownfield land within settlements, and says such proposals should be approved unless substantial harm would be caused.

More

The same paragraph asks decision makers to support the development of under-used land and buildings, and it names the kinds of place it means: space above shops, service yards, car parks, lock-ups and railway infrastructure. The weight settles nothing else. Flood risk, ecology, heritage, access, design and viability all stay live, and a site that fails one of them fails on that ground rather than on its brownfield status. Where the land is also protected for employment use, the release test is a different question again, set out in the guide to loss of employment land.

What is a brownfield land register?

A public list every local planning authority in England has had to keep since 2017, of previously developed sites it considers suitable for housing.

More

The duty comes from the Town and Country Planning (Brownfield Land Register) Regulations 2017, which required registers to be published by the end of that year. Part 1 holds every site the authority has assessed as suitable for residential development, whether or not it already carries permission. Part 2 is a subset of Part 1: the sites the authority has decided should carry permission in principle. The usual threshold for entry is a site of at least a quarter of a hectare, or one capable of taking at least five dwellings, though smaller sites can be entered. Absence from a register proves nothing: entry is the authority's decision and coverage is patchy.

What is permission in principle?

A consent that settles three things and no others: location, land use, and the amount of development. Everything else waits for technical details consent.

More

It arrives by one of two routes, on application or by the authority entering a site in Part 2 of its brownfield land register. On application it is decided in five weeks and lasts three years by default; through a register it lasts five. Technical details consent then follows, with ten weeks for major development and five for anything else. The route is deliberately narrow. It is closed altogether to development needing environmental impact assessment, to habitats development, to householder work and to minerals, and the application route is closed to major development, which means ten homes or more, a thousand square metres or more of floor space, or a site of a hectare or more. On heavily constrained land the principle cannot really be separated from the detail, which is why a full or outline application stays the realistic route.

Who is liable for contamination on land I buy?

In planning terms the developer and the landowner. Responsibility for securing a safe development rests with them, not with the authority that grants the permission.

More

A separate regime sits behind that one. Part IIA of the Environmental Protection Act 1990 lets a local authority identify land as contaminated where significant harm or significant pollution of controlled waters is being caused, or where there is a significant possibility of either. Liability falls first on whoever caused or knowingly permitted the substances to be there, and where no such person can be found it can reach the current owner or occupier. Planning does not run that regime, but it sets a floor against it. The working standard is suitability for the intended use, so the same ground can need one thing for housing and another for a warehouse. What to ask for before the money moves is set out in the guide to buying land.

Does biodiversity net gain apply to brownfield sites?

Yes, and neglected land is often the hardest place to deliver it, because years of doing nothing can produce habitat of real ecological value.

More

The statutory objective is at least a ten per cent increase in biodiversity value, and a biodiversity gain plan has to be approved before development may lawfully begin; the authority has eight weeks to approve or refuse one unless a longer period is agreed. Exemptions changed on 6 August 2026: a site of 0.2 hectares or less inside the red line is now exempt, but that exemption falls away if priority habitat on the site would be harmed. Open mosaic habitat on previously developed land is itself a priority habitat, and it is exactly what a long-vacant yard or siding grows. So the small-site exemption is least reliable on the sites that look emptiest. There is more in the net gain guide.

Does a brownfield site still need a flood risk assessment?

In Flood Zones 2 and 3, for all development. In Flood Zone 1, on sites of a hectare or more, and on smaller ones where another trigger applies.

More

The other triggers are critical drainage problems identified by the Environment Agency, land a strategic flood risk assessment puts at increased future risk, and land at risk from other sources where a more vulnerable use would be introduced. The sequential test is a separate question, and it applies however developed the land already is. It asks whether reasonably available sites exist at lower flood risk within an area of search the authority defines. Where they do, permission can be refused on that ground, and where the sequential and exception tests are applied and not met, development should not be allowed. Neither being previously developed nor a housing shortfall exempts a site: guidance is explicit that the absence of a five-year housing land supply is not a relevant consideration in applying the test to an individual application, though housing can still weigh in the wider balance. Why a site fails in principle is covered in the guide to why development sites fail.

Can affordable housing be reduced when a vacant building is reused?

Often, yes. National policy says that where vacant buildings are being reused or redeveloped, any affordable housing contribution due should be reduced by a proportionate amount.

More

The mechanism is a credit equivalent to the existing gross floorspace of the vacant building, set against the floorspace of the new development. Guidance gives the arithmetic: a building of eight thousand square metres demolished as part of a ten thousand square metre scheme leaves a contribution of a fifth of what would otherwise be sought. It does not apply to a building that has been abandoned, and abandonment turns on the condition of the property, how long it stood unused, whether anything happened there in between, and what the owner intended. Authorities also look at whether a building was emptied in order to claim the credit. On the right conversion this is worth more than any move a designer can make.

Written by

Rickett Architects

A RIBA Chartered practice, working since 1970, with more than 2,500 projects behind it. Our senior architects take projects from first survey through planning to completion, for private clients, developers and landowners across the Midlands and well beyond it.

Tell us about your project

Got a brownfield site?

A Senior Architect will reply. We will give you an initial appraisal and guide you as to what to do next.

Your enquiry will go directly to a Senior Architect.

Thank you. A Senior Architect will reply personally.
Something went wrong sending this. Please call 01926 967 090 or email studio@rickett.co.uk.