There were physical hurdles alongside the heritage ones. The only workable access meant forming a junction onto Longmoor Road and replacing the public parking lost from the existing layby, to the satisfaction of the county highway authority. Surface water drainage was complicated by levels and by a strip of third party land along the rear boundary. And ecological constraints across part of the site meant the land could not simply be developed end to end.
The full story
Greene King came to us with a parcel of land that had defeated everyone who had tried it. Pre-application advice in April 2022 tested eight dwellings and came back with the same themes the refusals had turned on: the setting of the listed building, the character of the conservation area, and the continued viability of the public house next door. That advice was the useful part of the job. It told us the ceiling was not a number the council had in mind, but an effect it wanted avoided.
So the scheme was designed downwards. We issued concept designs in July 2022 and worked the layout back until the homes occupied only the western edge, with the trees and a landscaped buffer left between them and the inn. By February 2023 it had settled at four houses, with the access road and services deliberately laid out so a later phase could come forward without disturbing what was built first. That phasing was driven by ecology, not by yield.
The architecture was pitched to disappear. Lowered eaves to hold the apparent scale down, red brick with hung red clay tile, small clay tile roofs, painted timber windows and traditional boundary walls, with render and applied finishes avoided. Design changes continued through determination: two of the four houses were reduced to a smaller two and three bedroom type, private amenity space on plot one was increased, and the entrance gates and wall were dropped. The Royal Anchor is a working pub with a kitchen, a garden, deliveries and late hours, so the homes were planned so that pub and residents could sit alongside one another, an issue that had sunk earlier applications.
We produced the full planning drawing package and the RIBA Stage 3 Design and Access Statement, and coordinated our design with the wider consultant team so the application arrived as one coherent proposal. We did not run the application and we did not write the heritage case. Permission was granted on 25 September 2024.