One of the consented house types, and a visualisation rather than a photograph. The last drainage condition cleared in August 2015, the developer started on site, and the homes were later built out by others. They are occupied today.
The full story
The site was a tight brownfield infill plot off Laundry Lane, on the established residential edge of Leominster: about 0.95 hectares of overgrown scrub and dilapidated outbuildings, hemmed by housing on two sides and the former Orphans Press works to the north-west. It had a single road frontage, a watercourse along its eastern edge, and surface water to resolve on a falling site before anything could be laid out.
The Wrekin Housing Group needed it to become an affordable-led scheme, and an affordable-led scheme only works if the number, mix and density of homes can fund the affordable housing and be built to budget. So the ambition counted for nothing until a permission was both granted and deliverable. The scheme had to read as a natural part of the neighbourhood, win a clean consent, and resolve highways and drainage before a spade went in the ground.
Before committing to a layout we tested how many homes the site could carry against the council's likely position and the viability the affordable mix demanded. The design grew from what would actually get consent: brick houses of a storey and a half, two storeys and two and a half storeys, extending the grain of the neighbouring streets, arranged around a single street designed for adoption, with parking drawn to the side and rear so the street scene stays uncluttered.
We prepared the scheme design, the Design and Access Statement and the full application, and acted as planning agent throughout. An officer concern over density and mix met a flat constraint: to win consent, the scheme came down from 44 homes to 41, the number the council would grant and the site would carry. Herefordshire Council granted full planning permission for all 41 homes on 17 December 2014, under reference P140665/F, with 22 conditions attached.
A planning permission is not a buildable site. The highway authority required the vehicular link to Jacques Road to be removed, so we reworked the road layout with the project engineer and took it back through a variation of condition 2, approved in April 2015 under reference P150668/F, with the new street designed for adoption.
Surface water was the slowest battle. The drainage strategy ran through Welsh Water as a Section 104 sewer requisition alongside a Section 38 road adoption, with the council's land-drainage consultant on the detail, and the last drainage condition cleared only in August 2015.
Across all of it we were the hub for around fourteen pre-start conditions, pulling together the engineers, ecologists, contamination and acoustic consultants, and produced the working-drawing set for every plot with design-stage SAP, Code for Sustainable Homes and Secured by Design built in.
With the conditions discharged, the developer could start on site: a scheme genuinely buildable, not just permitted. The homes were later built out by others and are occupied today. For a registered provider the value was certainty, a permission designed to be granted and then made ready to build before the programme depended on it.